 |
Originally published as a Consultant's Connection
column in Pro AV Magazine
|
Writing
AV Specifications
Adapting the CSI
construction specification model to work for AV systems.
By Tim Cape, CTS-D
The MasterFormat has been the default
structure for building
design specifications for decades and has worked well for the
traditional building
trades. But when it comes to pro AV, the structure of the new
MasterFormat 04
approved this year by the Construction Specifications Institute (CSI,
www.csinet.org) still isn't as friendly to our systems as it is to
traditional
bricks-and-mortar systems.
A number of AV industry professionals
(including me and
other representatives from the International Communications Industries
Association and the National Systems Contractors Association)
contributed,
commented, and participated in working with CSI to hammer out the AV
and
related sections. Although we still didn't get what we really wanted in
the
specifications structure (nor did some other trades), the end result is
a
workable one.
Specifications are important from the
designer's standpoint
in three important ways: they document the standards and goals for the
system installation,
play an important part (along with the system drawings) in allowing
bidders to
start on an even playing field during the bidding process, and
ultimately
become the binding contract between the owner and integrator in the
installation phase of the project.
Sections and Parts
In the new and the old MasterFormat,
there are separate
sections for materials such as reinforcing steel, wood paneling, metal
stud
framing, acoustical panel ceilings, doors, operable partitions, and —
of course
— bricks and mortar. There are equipment sections for HVAC fans, pumps
and
piping, electrical transformers, and door chimes as well as
non-building
equipment sections such as laundry equipment, copiers, and kitchen
appliances.
You'll also find more system-oriented sections for items such as
elevators and
escalators, which are still relatively easy to specify as a unit from a
system
level.
Three parts are generally used within
each section.
"Part 1 - General" includes administrative elements of the section
such as submittal requirements, warranty requirements, delivery,
storage
requirements, etc. "Part 3 - Execution" details preparation for
installation, how the item is to be installed and tested, and defines
the
item's quality issues. However, "Part 2 - Products" (sometimes titled
"Materials"), is often the most problematic for pro AV systems. For
most construction subsystems, (including electrical, mechanical, and
plumbing)
as well as many low-voltage systems, the list of materials or products
in any
given section is relatively short. It may be one item, a list of
similar items,
or performance information referring to a schedule of products located
on the
drawings.
In the early development of the new
MasterFormat, CSI worked
with schemes that would have required us to provide a complete section
with
Parts 1, 2, and 3 for each product. While this may work for components
and
systems with a short materials list, pro AV becomes more of a challenge
under
this scheme because we may have hundreds of products specified within a
single
system. The final MasterFormat 04 includes a section for Integrated
Audio-Video
Systems and Equipment (24 41 16) for AV, plus a couple of other related
sections. Subsections were also added for several individual space
types such
as conference rooms, classrooms, and auditoriums. Although these may
not be
useful to many specification writers, specifications can be written
based on
the main section alone without specifying systems by room or room type
as
listed in the MasterFormat.
Adapting AV
In the early days, as pro AV
integration started to develop
and become part of the building industry, AV consultants had to adapt
to the
way bricks-and-mortar drawings and specifications were prepared in the
construction industry. One issue that has been problematic is the
listing of
materials and equipment quantities. The general approach in the
traditional
architectural and engineering disciplines is to show something only
once in a
set of documents, and equipment quantities aren't listed at all.
For example, if gypsum wallboard can
be counted on a
drawing, the architect doesn't list quantities of material. Instead,
the
contractor does a take-off of how long and high the walls are and
calculates
the square footage of gypsum board and other materials required. In
this case,
the contractor can do the take-off fairly easily using the drawings,
and then
update the figure only when formal addenda or change orders are issued.
To adapt to this traditional model of
writing specifications
for AV, the first change we had to make to the traditional spec-writing
structure was to have one section per system or space, instead of one
section
for each individual product. Another approach we used was to have one
section
for everything, because the "Part 1 — General" and "Part 3 —
Execution" information very often would generally apply across the
entire
system. But this solution created another problem because pro AV
systems often
include 100 to 200 products. Even if we list 100 products and their
specifications and alternatives in Part 2, the contractor bidding on
the system
must examine the product list for the product specifications, and then
look at
the drawings to get the configurations and the quantities of each item.
Unfortunately, this isn't easy. Different consultants organize their
drawings
differently, and sometimes a repeated system or component shown once on
the
drawings may actually represent many more units of that item.
This causes a lot of problems for bid
projects, particularly
ones that are large and complex. Consultants who have been working on a
project
for a year or two would give bidding contractors perhaps two to four
weeks
(sometimes less) to develop bids and expect a bidding contractor to
review,
understand, and price the whole system in that short amount of time.
While this
may put an extra burden on the contractor, the argument is made that
the
contractor will need to understand the system to bid it, and forcing
integrators to dig deeply into the bid documents to determine
quantities will
make that possible.
To quantify or not to quantify
However, the reality is different in
most cases. If the
integrator takes the time to go through a large, complex bid set, the
integrator may still not get the job. On top of that, it's likely that
a
competing integrator who is overloaded or inexperienced will miss
something in
developing a bid and get the job simply because it was unintentionally
underbid. Another problem is that the distribution of bids may be very
wide
because of the way various integrators interpreted the quantities.
So, what's the solution? Provide a
list of equipment quantities
in the bid documents. Because every project needs to be budgeted before
it's
bid and the consultant needs to develop a list with equipment
quantities anyway,
why not publish the list with the bid? In my experience, including such
a list
can significantly improve the bid process. It provides a much tighter
bid
distribution in the pricing and reduces the chance that an integrator
will
severely under- or overbid the job.
But what happens if the quantities in
the list are incorrect
or if there's a conflict with the drawings? The quantity list makes the
course
of action much clearer if it's noted as the prevailing information
source. This
is generally preferred to the haggling that can result over the way
items may have
been represented in the drawings.
With or without a list of quantities,
we'll continue to work
with MasterFormat and some of its limitations in writing specifications
for pro
AV systems. The good news is that with a little creativity, we can
adapt it to
work for us in this age of technology-rich facilities.
|